Project:                                                NACAP QSN3 Pipeline Camp Installation and Maintenance

Client:                                                  

Location:                                              Roma - Moomba

Duration:                                             12 Months

LTI/ MTI:                                              0

Recordable Incidents:                    0

Scope of Work:                                

The supply of labour and plant required for the construction, shifting and maintenance of 11 Camps between Roma and Moomba.

                      

Project Activities:                                            

  • Site Development and associated civil works,
  • Installation, disassembly and maintenance of Camp Plumbing and Drainage
  • Installation and maintenance of Gas appliances
  • Installation and maintenance of Refrigeration Appliances
  • Installation, disassembly and maintenance of Camp Electrical Network
  • Installation of Building Tie-downs
  • Installation, disassembly and maintenance of Sewerage Treatment Plants
  • Installation, disassembly and maintenance of Reverse Osmosis Plants
  • Construction of Concrete Walkways, Skillion Roofing and Fencing
  • Procurement and Logistics
  • Electrical, Plumbing and Gasfitting Certification
  • Project Management and Project Liaison with Client Representatives
  • Development and maintenance of Management Plans
  • Commissioning of Installation